What Is a Bill of Quantities? Format, Example and Types
What a bill of quantities (BOQ) is, what goes in each column, a worked example built from a takeoff, the two main types, and how it differs from a takeoff, an estimate and a bill of materials.
The short answer: a bill of quantities (BOQ, or BQ) is a document that lists every item of work in a construction project with its description, unit of measurement and measured quantity, and a space for a rate and an amount. It is built from a takeoff of the drawings. In tendering, every bidder prices the same BOQ, so their prices can be compared line by line.
What is in a bill of quantities
Every line of a BOQ has the same columns:
- Item number, so a line can be referred to in questions, variations and payment claims.
- Description of the work, specific enough to price: not "drywall" but "1/2 in gypsum board to walls, taped, filled and sanded ready for paint".
- Unit of measurement: square feet or square metres for areas, linear feet or metres for lengths, cubic yards or cubic metres for volumes, and "each" or "no." for counted items.
- Quantity, measured from the drawings.
- Rate, the price per unit, filled in by whoever prices the bill.
- Amount, the quantity multiplied by the rate.
Lines are grouped into sections, usually by trade or work section (substructure, framing, drywall, finishes, electrical), with preliminaries and general items at the front and a summary at the back that totals each section.
A worked example
The quantities below come from the bedroom in our construction takeoff example: a 12' × 15' room with an 8' ceiling, one door and one window. The rates are illustrative only, to show the arithmetic; they are not market prices.
| Item | Description | Unit | Qty | Rate | Amount |
|---|---|---|---|---|---|
| 1 | 1/2 in gypsum board to walls, taped and finished | sq ft | 400 | $2.50 | $1,000.00 |
| 2 | 1/2 in gypsum board to ceiling, taped and finished | sq ft | 180 | $2.80 | $504.00 |
| 3 | Two coats latex paint to walls | sq ft | 400 | $1.20 | $480.00 |
| 4 | Two coats latex paint to ceiling | sq ft | 180 | $1.30 | $234.00 |
| 5 | Laminate flooring, supply and lay | sq ft | 180 | $4.00 | $720.00 |
| 6 | Baseboard, supply and fix | lf | 51 | $3.50 | $178.50 |
| 7 | Interior door, frame and hardware | each | 1 | $450.00 | $450.00 |
| 8 | Duplex receptacle, supply and install | each | 4 | $85.00 | $340.00 |
| Section total | $3,906.50 |
Two things to notice. The quantities are the measured quantities from the drawing (400 sq ft, not 14 sheets): waste and sheet sizes are the pricer's job, built into the rate. And because every bidder prices the same 400 sq ft, a low rate on item 1 shows up as exactly that, not as a different measurement.
The two main types of BOQ
- Firm bill of quantities. Prepared when the design is complete enough to measure everything accurately. The quantities are expected to hold, and the priced bill becomes a contract document.
- Approximate (provisional) bill of quantities. Prepared when the design is not finished. The quantities are best estimates, and the work is remeasured as it is built and paid on the actual quantities at the tendered rates.
You will also see provisional sums inside a bill: amounts set aside for work that cannot be defined yet, such as an allowance for light fittings the client has not chosen.
Who prepares a bill of quantities
On larger projects a quantity surveyor (QS), working for the client, measures the drawings and prepares the bill, and contractors price it. On smaller jobs and in subcontract work, the contractor's estimator often does the takeoff and builds their own bill of quantities to price from. Measurement normally follows a published standard so everyone measures the same way: NRM2 from RICS in the UK, the Australian Standard Method of Measurement (ASMM), and CESMM4 for civil engineering work.
In the US, owner-issued bills of quantities are less common on building work. Contractors do their own takeoff, and the priced breakdown submitted with payment claims is usually a schedule of values.
BOQ vs takeoff vs estimate vs bill of materials
| Document | What it is | Who uses it |
|---|---|---|
| Takeoff | The measuring: every length, area, volume and count read from the drawings | Estimator or QS |
| Bill of quantities | The takeoff organised into described, numbered items with units, ready to price | Client's QS issues it; bidders price it |
| Estimate | The priced result: quantities × rates, plus overheads and margin | Contractor |
| Bill of materials | A list of the materials to buy, by product and pack size, often with waste | Purchasing, suppliers, manufacturing |
The difference between a BOQ and a bill of materials causes the most confusion. A BOQ describes work to be done and priced, including labour; a bill of materials lists the products to buy. "400 sq ft of drywall, taped and finished" is a BOQ line; "14 sheets of 4 × 8 gypsum board" is a bill of materials line.
How to prepare a bill of quantities
- Collect the drawings and specification, and note the revision of each sheet.
- Do the takeoff, measuring each item once with a record of how it was measured.
- Group the quantities into sections by trade or work section.
- Write descriptions that state the material, size and extent of the work, following the measurement standard you are using.
- Number the items and add preliminaries, provisional sums and a summary.
- Price it (if you are the contractor), or issue it for pricing.
Steps 2 to 4 are where most of the time goes. In ContractorCounter the takeoff and the bill are the same thing: every area, length and count you measure on the PDF becomes a bill of quantities line that updates when the drawing changes, and rates turn it into a priced quote. See how it works in construction takeoff software.
FAQ
What is a bill of quantities in construction? A document listing every item of work with its description, unit and measured quantity, so the work can be priced. In tendering, all bidders price the same bill, which makes their prices comparable line by line.
What are the two types of BOQ? A firm bill of quantities, measured from a complete design and expected to hold, and an approximate (provisional) bill, measured from an incomplete design and remeasured as the work is built.
What is the difference between a quantity surveyor and an estimator? A quantity surveyor usually works for the client, measuring the drawings, preparing the bill of quantities and managing cost through the project. An estimator usually works for the contractor, pricing the work to win it. On small jobs one person often does both.
Is a bill of quantities the same as a bill of materials? No. A bill of quantities describes work to be done and priced, including labour. A bill of materials lists the products to buy, in pack sizes, with waste.